Why the construction works take so much information
On the site of a block, dozens of crews work one after the other within a few months. The roofer cannot start before the shell is finished, the screed layer not before the electrical and plumbing pipes are in, and the kitchen fitter not without the technical plan of the kitchen the buyer has chosen.
So each crew needs the right drawings: the working drawings in PDF and DWG, the sill details for the shell, the single-line diagram for the electrician, the technical bathroom drawing for the plumber. And each crew has to know where each home is. If a drawing or a buyer choice is missing, the next crew stands still.
With IRP in Lean ERP you record the works as a sequence of steps, with per step the information that belongs to it. Below is an example of such a step plan. You can model your own processes within IRP.